EN - صياغة العقود التجارية
A supplier and a buyer sign a two-page supply contract containing a clause that reads: “The buyer shall pay a penalty of 2% for each week of delay in payment.” Months later, payment is late and the supplier claims the penalty, only to discover that the law does not permit agreeing in advance on compensation where the obligation is to pay a sum of money. This shows that it is not enough for a contract to be in writing; it must be drafted in the language of the law by which it will be interpreted.
Drafting commercial contracts in Saudi Arabia means turning the parties’ agreement into clauses that hold up under the Civil Transactions Law: valid elements (sound consent, a possible and specified subject matter, and a lawful cause), defined obligations, and compensation, termination and exceptional-circumstances clauses that do not violate mandatory rules, together with written evidence that meets the Law of Evidence and a clear means of resolving disputes.
Key Points
- The Civil Transactions Law (M/191) is the general reference for contract rules, from which the rules on formation, interpretation, termination and compensation are drawn.
- A penalty clause is permitted, but it is not valid where the obligation is to pay a sum of money, and the court may reduce or increase it in specified cases (Articles 178 and 179).
- The parties may not agree to depart from the “exceptional circumstances” rule, and negotiating under it does not permit suspending performance (Article 97).
- An express termination clause does not dispense with formal notice unless the waiver of notice is expressly stated (Article 108).
- A transaction worth more than 100,000 must be proven in writing (Article 66 of the Law of Evidence).
What Is the Legal Framework for Drafting Commercial Contracts in Saudi Arabia?
The Civil Transactions Law was issued by Royal Decree No. (M/191) dated 29/11/1444 AH (2023), published on 1/12/1444 AH, and came into force 180 days after its publication (Article 721). It is the first comprehensive Saudi codification of contract theory: formation, defects of consent, subject matter and cause, effects, termination and compensation. It does not operate alone; a commercial contract usually intersects with three other laws:
- The Law of Evidence issued by Decree (M/43) dated 26/5/1443 AH: it determines when writing is required and the evidentiary weight of correspondence and digital evidence. It is explained in our article on types of evidence and the weight of digital evidence.
- The Arbitration Law issued by Decree (M/34) dated 24/5/1433 AH: it requires the arbitration agreement to be in writing, failing which it is void (Article 9).
- The Commercial Courts Law issued by Decree (M/93) dated 15/8/1441 AH: it governs the procedure for hearing commercial disputes where arbitration has not been agreed.
The commonly cited reference to “the Commercial Law (the Commercial Court Law)” is outdated; the procedural reference in force is the Commercial Courts Law.
Elements of the Contract and Conditions of Its Validity: Consent, Subject Matter and Cause
Consent and Its Defects
A contract is formed by matching offer and acceptance, but consent may be vitiated by four defects regulated by the Law, each with a precise condition:
- Fundamental mistake: allows a request for annulment if, without it, the contracting party would not have agreed to the contract (Article 57), provided the other party made the same mistake, knew of it, or could easily have discovered it (Article 58). A clerical error in calculation or writing does not affect the contract (Article 59).
- Misrepresentation (taghrir): the term the Law adopted instead of “fraud”, commonly used in writings; it includes fraudulent means and deliberate silence about a matter which, had the misled party known of it, would have prevented the contract (Article 61).
- Duress: an unlawful threat, by physical or moral means, that induces a person to act (Article 64).
- Exploitation: exploiting an evident weakness or pressing need to conclude a contract involving gross unfairness; the claim must be filed within 180 days of contracting, otherwise it will not be heard (Article 68).
Subject Matter and Cause
The subject matter of the obligation must be possible in itself, not contrary to public order, and specified by its identity or by its type and quantity, or capable of being specified; otherwise, the contract is void (Article 72). The contract may include any condition the parties agree on that meets these requirements; a void condition is void on its own, and a contracting party may request annulment of the contract if it is shown that he would not have agreed to it without that condition (Article 74). The cause is presumed lawful unless proven otherwise (Article 76), and the contract is void if the motive is unlawful and was stated or indicated by the circumstances (Article 75).
Key Clauses in Commercial Contracts and Their Legal Basis
The following table links each common clause to the provision through which a judge or arbitrator will read it, and to the mistake that recurs in drafting it:
| Clause | What It Must Settle | Legal Basis | Common Mistake |
|---|---|---|---|
| Parties and representation | Capacity and the limits of the signatory’s authority | Article 501 (agency in contracting) | Signature by a manager without authority and without a registered delegation |
| Subject matter and specifications | Quantity, quality and the acceptance standard | Articles 72 and 73 | Leaving quality without a standard, so the obligor is bound only to average quality |
| Liquidated damages | The pre-agreed amount for non-monetary breach | Articles 178 and 179 | Applying it to late payment of a sum of money |
| Exemption from liability | Limits of contractual liability | Article 173 | An exemption that covers fraud or gross negligence |
| Termination | Breaches that justify termination, and formal notice | Articles 107 and 108 | Omitting an express waiver of formal notice |
| Exceptional circumstances | The negotiation mechanism and its duration | Article 97 | A clause preventing any adjustment of the obligation however unbalanced it becomes |
| Dispute resolution and confidentiality | The forum and the governing law | Article 113; Article 9 of the Arbitration Law | An unwritten or ambiguous arbitration clause |
Penalty Clauses: When Are They Valid and When Do They Fail?
“The contracting parties may determine in advance the amount of compensation by stating it in the contract or in a subsequent agreement, unless the subject of the obligation is a sum of money, and formal notice is not required for the compensation to be due.”
Civil Transactions Law, Article 178
Two consequences of this text are overlooked by many templates. First, liquidated damages suit non-monetary obligations, such as delay in delivery or completion, and do not suit compensation for late payment of a sum of money. Second, the amount is not final: it is not due if the obligor proves that the obligee suffered no damage; the court may reduce it if it is excessive or if part of the obligation has been performed; and it may increase it to the amount of the damage if the damage exceeds it because of fraud or gross negligence. Any agreement to the contrary is void (Article 179).
If compensation is not set in the contract, the court assesses it, and in a contractual obligation the obligor, unless he has committed fraud or gross negligence, is liable only for damage that could normally have been foreseen at the time of contracting (Article 180). It is therefore useful for the contract to state expressly the damage the parties foresee, such as the loss of a contract with a third party, so that it falls within what is foreseeable. For the general rules on compensation, see the rules on compensation for damage under the Civil Transactions Law.
Limiting and Excluding Liability
The parties may agree to exempt the obligor from compensation for failure to perform or delay in performing a contractual obligation, except where this results from his fraud or gross negligence; exemption from liability for a harmful act is not permitted (Article 173). A clause stating that “the supplier shall not be liable for any damage whatever its cause” is therefore void to the extent it exceeds these limits.
Termination and the Express Termination Clause
In bilateral contracts, if one party breaches, the other may, after giving formal notice, request performance or termination, with compensation where warranted, and the court may refuse termination if the unperformed part is of little importance (Article 107). The parties may agree on termination without a court judgment, but such an agreement does not dispense with formal notice unless it expressly waives it (Article 108). Formal notice itself may be given by any agreed or prescribed means of notification, including filing a lawsuit (Article 177). The contract should therefore specify the means of notice, such as an email address named in the contract.
Exceptional Circumstances and Impossibility of Performance: The Difference
“If general exceptional circumstances arise that could not have been foreseen at the time of contracting, and their occurrence makes performance of the contractual obligation onerous for the obligor so as to threaten him with grave loss, he may, without unjustified delay, invite the other party to negotiate.”
Civil Transactions Law, Article 97 (Paragraph 1)
The text sets out a three-stage path: negotiation first, without suspending performance; then, if no agreement is reached within a reasonable time, the court may reduce the onerous obligation to a reasonable level; and any agreement contrary to the article is void. This differs from impossibility: if performance becomes impossible for a cause beyond the obligor’s control, the obligation and its counter-obligation are extinguished and the contract is terminated automatically; if the impossibility is partial or temporary in a contract performed over time, only the impossible part is extinguished (Article 110). It is a mistake to combine the two situations in a single clause called “force majeure” without distinguishing their effects.
Interpretation, Adhesion Contracts and Clauses That Survive Termination
Clear wording may not be departed from on the pretext of interpretation; where there is room for interpretation, the common intention is sought, and doubt is resolved in favor of the party bearing the obligation, and in adhesion contracts in favor of the adhering party (Article 104). The court may amend unfair terms in adhesion contracts or exempt the adhering party from them (Article 96). A useful provision for drafters is that the dispute resolution clause and the confidentiality clause do not lapse upon termination of the contract unless otherwise agreed (Article 113).
Writing and Evidence: Why Drafting Affects Proof
Any transaction worth more than 100,000, or of unspecified value, must be proven in writing, and witness testimony is not accepted for it unless there is an agreement or provision to the contrary (Article 66 of the Law of Evidence). The parties may agree on specific rules of evidence, provided the agreement is in writing and does not violate public order (Article 6). In practice, digital evidence derived from a digital means specified in the contract is binding on its parties unless proven otherwise (Article 57). Naming the email address or platform approved for correspondence in the contract is therefore not a formality; it raises the evidentiary weight of that correspondence.
A hypothetical example: A contract for store fit-out works worth 400,000 contains a penalty clause of 1,000 for each day of delay in delivery, an express termination clause “without the need for formal notice”, and correspondence through an email address named in the contract. The contractor was 30 days late. The penalty clause here relates to a non-monetary obligation, so it is valid, but the contractor may request a reduction if he proves it is excessive or that he performed a large part of the works. Termination without notice is sound because the waiver is express. The delay messages exchanged through the named email address serve as digital evidence binding on both parties.
Common Mistakes in Drafting Commercial Contracts
A “late payment penalty” as a percentage of the debt: Article 178 expressly excludes an obligation to pay a sum of money from pre-agreed compensation. The alternative is to tighten the payment terms themselves: clear due dates, security, and a right to suspend performance or terminate upon delay.
A clause preventing any adjustment of the obligation in exceptional circumstances: it is void under paragraph 4 of Article 97. More useful drafting regulates the negotiation procedure, its duration and its documentation, rather than excluding the rule.
Checklist Before Signing a Commercial Contract
- Verify the signatory’s capacity and authority, and attach the delegation or company resolution where needed; see the conditions and limits of a legal power of attorney.
- Define the subject matter with measurable specifications and an acceptance standard.
- Separate monetary and non-monetary obligations before drafting any penalty clause.
- Specify the means of formal notice and notification, and expressly waive notice if you want immediate termination.
- Regulate negotiation in exceptional circumstances instead of trying to exclude them.
- Write the arbitration or jurisdiction clause clearly, and name the governing law in international contracts.
Some contracts are subject to special rules that take precedence over the general rules, such as the franchise agreement, whose law imposes specific clauses and prior disclosure; this is explained in the rules on franchise agreements and the disclosure document. Company formation contracts and shareholders’ agreements are governed by the Companies Law; see the steps for establishing a company in Saudi Arabia and the rules on corporate governance and directors’ duties.
Frequently Asked Questions
Can a penalty clause be set for late payment of a sum?
Pre-agreed compensation is not valid where the obligation is to pay a sum of money, under Article 178 of the Civil Transactions Law. A penalty clause suits non-monetary obligations such as delivery and completion. To protect the creditor’s right to payment, use payment security, precise due dates, and a right to suspend or terminate with formal notice.
Can the court change an agreed penalty clause?
Yes. At the obligor’s request, the court may reduce it if the obligor proves it is excessive or that part of the obligation has been performed, and it is not due at all if the obligor proves that the obligee suffered no damage. At the obligee’s request, the court may increase it to the amount of the damage if the damage exceeds it because of fraud or gross negligence. Any agreement to the contrary is void (Article 179).
What is the difference between exceptional circumstances and force majeure in a contract?
Exceptional circumstances make performance onerous, threatening grave loss, but not impossible; they open the door to negotiation and then to the court reducing the obligation to a reasonable level (Article 97). Impossibility for a cause beyond the obligor’s control extinguishes the obligation and its counter-obligation, and the contract is terminated automatically; it may be partial or temporary (Article 110).
Is an electronic contract or an exchange of messages enough to prove an agreement?
Digital evidence has the same status as writing for purposes of proof (Article 55 of the Law of Evidence). It is binding on the parties unless proven otherwise if it was issued under the Electronic Transactions Law or the E-Commerce Law, or derived from a digital means specified in the contract, or from an authenticated or publicly available means (Article 57).
Must an arbitration clause be in writing?
Yes. The arbitration agreement must be in writing, failing which it is void (Article 9 of the Arbitration Law). It is considered in writing if it is contained in a document issued by the parties, in documented correspondence or in electronic communications, and a clear reference in the contract to a document containing an arbitration clause is treated as an arbitration agreement.
Do you need legal advice on drafting your commercial contract?
The team at Aman Compliance Law Firm and Legal Consultations provides advice and representation in drafting and reviewing commercial contracts, and each case is assessed on its own facts and documents. You can view our Commercial or Partnership Contract Drafting Service.
Request a ConsultationReferences
- Civil Transactions Law, issued by Royal Decree No. (M/191) dated 29/11/1444 AH: Articles 57–76, 94–113, 173, 176–180, 501 and 721. The law’s page at the Bureau of Experts
- Law of Evidence, issued by Royal Decree No. (M/43) dated 26/5/1443 AH: Articles 6, 55, 57 and 66. The law’s page at the Bureau of Experts
- Arbitration Law, issued by Royal Decree No. (M/34) dated 24/5/1433 AH: Article 9.
- Commercial Courts Law, issued by Royal Decree No. (M/93) dated 15/8/1441 AH.
Notice: This article is for general legal awareness under the laws in force on the date of last review. It is not legal advice and is no substitute for having your case reviewed by a licensed lawyer. Laws and their regulations are subject to amendment.